Friday 17 August 2012

Bathroom Ledbury

Bathroom to recce in Ledbury tonight with a view to installing in September i'll post photos later.

Did the recce got the job to tile the walls floor and fit the bathroom suite quoted £900.

DAY ONE


Start State 


Start State



Tiles Off


Tiles Off



Service Valve Fitted

Pipe Work For Shower 

Day Two


Started Tiling

Bath Half full to put it at the correct height for the Sealant to sit properly .

Day Three


All tiled just need to grout and then the floor.




Last Day tomorrow need to grout and finish the walls, then the floor and finally fit the white goods.

Day Four Job Done






All done customer happy.